Friday, 17 December 2010

Worcester Park Roadworks Map

I've been attempting to work out the scale of the upcoming roadworks disruption and turned to Google Maps to help visualise it. While all those who are into NLP discuss my preferred learning style the rest of us can try and work out whether we'll ever be able to go shopping again.

If you click on the image on the left it should take you to a Google map with lines and clicky things showing where the works will be taking place. It's my best endeavour at trying to collate the information, which comes from the Kingston Council page here, so do let me know if I've missed, misplaced or mucked anything up. So, in no particular order:

Phase One works will start in January 2011 and are expected to be completed in eight weeks. A traffic management scheme will be in place throughout the works that will require the temporary closure of three roads – Green Lane, Lynwood Drive and Park Terrace - and one way working underneath the railway bridge that will be controlled by temporary traffic lights.

‘Streets For People’
Who:
Sutton Council (with funding from Transport for London)
Where: Central Road between junctions with Green Lane and Lynwood Drive.
What: Works involve de-cluttering the footways, altering kerb lines, building speed tables and resurfacing footways.

Cast Iron Mains replacement
Who: Sutton and East Surrey Water
Where: Central Road between junctions with Green Lane and Balmoral Road.
What: Replace two mains along both sides of Central Road and the supply to each property in the area. This requires excavation of the carriageway and the temporary closure of the junction with Lynwood Drive.

Gas Mains Replacement
Who: Southern Gas Network
Where: Malden Road from the junctions with Motspur Park and Idmiston Road.

Replacement Sewer – Flood alleviation scheme
Who:
Thames Water
Where: Malden Road, Worcester Park from junctions with Park Terrace and South Lane.
What: The works would involve deep carriageway excavations, likely to occupy half the width of the carriageway, requiring some form of temporary traffic management.

‘Minor’ Traffic Management schemes
Who:
Kingston Council
Where: Two primary locations on Malden Road – junction with Motspur Park and Church Road.
What: Realignment of kerb lines and resurfacing of the highway.

Possible addition: Gas Mains Replacement
Where: Malden Way Southbound slip Road on A3 at Malden Roundabout

Monday, 13 December 2010

Two years of roadworks disruption in Worcester Park?

Hmmm... just when Sutton and East Surrey Water's little experiment in road works seems to be passing without much disruption dire prognostication of disruptions to come arrives from Kingston Council (aka "the people who cut down the trees" to those of us on the Sutton side) who really ought to know.

On the Kingston Council website it says:
“We have identified that there are a series of activities by a number of different agencies that will need to be completed in the next two years that will all affect traffic on the A2043 [Ed:Malden Road/Central Road].

“The simple fact is that these works cannot be carried out without causing some level of disruption. By working together we can reduce the completion time by some months and therefore minimise the disruption to road users and local residents.”

The total duration of all these works would be approximately two years if all the works followed one after the other in the traditional way. But all the agencies involved recognise that by working together, sharing our knowledge and expertise, we can deliver the best improvements for local people in the shortest time and by causing the least disruption.


And here comes the really good news!
The first project will be essential works to underground gas supplies either side of the railway bridge at Worcester Park Station, between Green Lane (London Borough of Sutton) and Park Terrace (The Royal Borough of Kingston upon Thames). Phase One works will start in January 2011 and are expected to be completed in eight weeks.

The works are part of the national Gas Mains replacement programme, replacing old iron pipes with new Polyethylene mains which will require excavation of the highway. A traffic management scheme will be in place throughout the works that will require the temporary closure of three roads – Green Lane, Lynwood Drive and Park Terrace - and one way working underneath the railway bridge that will be controlled by temporary traffic lights. Advance warning notices will be displayed in the area and residents will be kept updated of progress throughout the programme

Full article here:
http://www.kingston.gov.uk/information/news_and_events/news.htm?id=110203


Is this all part of Sutton Council's cunning plan to get us on Central Road side of the railway to shop in Sutton instead!?!?

Wednesday, 17 February 2010

Worcester Park renovation consultation

Is there an election coming up or something?? There seems to be a sudden upsurge in interest in the welfare of Worcester Park and although I'd love it to be because they've recognised us for being the fine, upstanding community that we are the part of me that sometimes reads Private Eye suspects there may be an ulterior motive.

First we were told that the long-promised traffic-light synchronisation was on its way, and more recently we've been told that there may be funds for flood defences in the offing. Now the dearly beloved recipient of all our Council Tax payments, the London Borough of Sutton, has started a consultation on a proposed £400,000 renovation of Worcester Park in conjunction with Kingston Council.

In a joint initiative between Sutton and Kingston Councils, residents are being asked what improvements they would like to see in the area. Their views will help create a plan that may include more pedestrian crossings, improved lighting and more street trees.
The public will also have their say on more extensive changes such as controlling the speed and number of cars that are allowed down certain roads. The streets being considered for improvement are Green Lane, Longfellow Road, Lincoln Road and Central Road.
The project is being funded by Transport for London under a scheme called Streets for People. It aims to improve the quality of local areas and make them a place where people feel comfortable walking, cycling and shopping.


Even Merton Council get to have a word in there:
Cllr William Brierly, Cabinet member for Planning and Traffic management on Merton Council said: "Although the consultation will not affect roads directly in our borough, any resulting improvements will impact on Merton. We support Sutton and Kingston in this initiative which should result in a more pedestrian- and cycle-friendly environment.
"We would welcome an improved pedestrian and cycle route joining Green Lane with Lower Morden Lane and Garth Road which would create better access across the borough borders. I would encourage as many people as possible to get involved and make their voice heard."


A little more information can be found in the local committee minutes from November 2009 here (point 940).

Unfortunately the page sharing this piece of news doesn't have a link to any consultation document or suggestions on how the likes of you and I can get involved and using the Sutton web site's search feature with the words "Worcester Park" and "£400,000" doesn't provide any information so perhaps one of our friendly local Councillors could point us in the right direction? As the consultation started on Monday and only runs until the 12th March it'd be a shame to miss out on the chance to put a word or two in.